Accordingly to the PMBOK Guide, Fourth Edition, Perform Quality Assurance is the process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used. Whereas, Perform Quality Control is the process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.

Thanks for the overwhelming response to the Quality Assurance vs Quality Control Quiz and the awesome suggestions for blog topics. Till date it has received double Nelson (222) responses. I really appreciate all the feedback. Let's review the answers to the questions. Feel free to question the answers!
  1. Deliverable - Perform Quality Control

    Quality Control is about reviewing the deliverables to ensure that quality standards are being met.

  2. Process - Perform Quality Assurance

    Quality Assurance is about the process used for creating the deliverables.

  3. Peer Review - Perform Quality Control

    Peer reviews are usually performed as part of quality control. They are very common in software development projects.

  4. Fishbone Diagram - Perform Quality Assurance, Perform Quality Control

    Fishbone Diagrams can be used in Quality Control to identify the factors contributing to potential quality problems or effects. Fishbone diagrams can also be used in Quality Assurance to identify the root cause of problems.

    This is one question that stumped most people.

  5. Audit - Perform Quality Assurance

    Audits are done to ensure that the quality standards established in the project plan are followed.

  6. Quality Control Measurements (as input or output) - Perform Quality Assurance, Perform Quality Control

    Quality Control Measurements are an output of Perform Quality Control, and an input to Perform Quality Assurance.

  7. Usually done by a group external to the project - Perform Quality Assurance

    Quality Assurance is usually performed by the Quality Assurance department or a group external to the project team. Quality Control can be performed by a Quality Control department (which can be external too), or can be done by the project team.

  8. Are the standards being followed? - Perform Quality Assurance

    Quality Assurance ensures that quality standards are being followed.

  9. Are the standards being met? - Perform Quality Control

    Quality Control checks whether standards are being met.

  10. Right First Time - Perform Quality Assurance

    Right First Time or Zero Defects is Step 7 of Phil Crosby's 14 Step Quality Improvement Process. Quality Improvement is usually associated to Perform Quality Assurance.

  11. Proactive - Perform Quality Assurance

    Quality Assurance tries to prevent problems, and hence considered proactive.

  12. Reactive - Perform Quality Control

    Quality Control finds the problems after the problems have occurred, and hence reactive.

  13. Capability Maturity Model Integrated (CMMI®) - Perform Quality Assurance

    CMMI is a process improvement model and associated to Process Analysis, which is a technique used in Perform Quality Assurance.

  14. Find defects - Perform Quality Control

    Perform Quality Control finds defects.

  15. Prevent defects - Perform Quality Assurance

    Perform Quality Assurance helps to prevent defects.

  16. Root Cause Analysis - Perform Quality Assurance

    Root Cause Analysis is a part of Process Analysis, which is a technique used in Perform Quality Assurance. This is a question that most people got wrong.

  17. Metrics - Perform Quality Assurance, Perform Quality Control

    Quality Metrics are an input to both Perform Quality Assurance and Perform Quality Control. This question is straight from the PMBOK Guide, but received only 50% correct responses. So, please do NOT ignore the PMBOK Guide.

  18. Executing Process Group - Perform Quality Assurance

    Perform Quality Assurance is a part of Executing Process Group, whereas Perform Quality Control is a Monitoring and Controlling process.

  19. Quality Checklists - Perform Quality Control

    Quality Checklists are an output of Plan Quality and an input to Perform Quality Control.

  20. Cost Benefit Analysis - Perform Quality Assurance

    Cost-Benefit Analysis is a technique used in Plan Quality, but can also be used in Perform Quality Assurance. Note that all Plan Quality and Perform Quality Control tools and techniques can be used in Perform Quality Assurance also.
Refer to the graph below for a quick snapshot of the quiz results by questions:

Please let me know your comments and suggestions. I welcome all feedback.

Image credit: Flickr / SMJJP

Related articles:

11 comments:

  1. Harry... thanks for the answers and explanation.

    ReplyDelete
  2. Hey Suresh,

    You are already PMP certified now. You know this stuff better than me :)

    Now it's your turn to develop some quizzes for me that I can post on the blog. Many quiz participants expressed interest in Procurement Management. So, why don't you develop a quiz on the contract types?

    Looking forward to your contribution. Talk to you in office tomorrow.

    Thanks.

    ReplyDelete
  3. Hi Harwinder,

    Did you get a chance to write an article on difference between Quality Control and Quality Assurance ? I couldn't find any in your notes section.

    ReplyDelete
  4. Hi Syed,

    I don't think I have a separate post on this topic. I thought that the answers to the quiz question would be sufficient to cover this topic. Let me know if you have any specific doubts.

    Thanks.

    ReplyDelete
  5. Hi Harwinder,

    The quiz in addition to your explanation to my query in the other post was good enough. Thanks for the help. Btw, just thought I should say this - you are doing a great job for the PM Community and great role model to look forward to :-).

    Thanks for all the help,

    Best Regards,
    Syed

    ReplyDelete
  6. Little late on this post. Have a question: if CMMI is quality assurance, how is peer review quality control??

    Peer review is a KPA in CMMI?

    Vinayak
    Envy.ram@gmail.com

    ReplyDelete
  7. Hello Ram,

    I'm not sure I understood your point clearly.

    Peer review is a quality control tool, and all quality control tools can also be used in quality assurance.

    Regards,

    ReplyDelete
  8. Harwinder,

    Thanks for the response, your answer makes perfect sense to me

    Regards,

    ReplyDelete
  9. Hi Harwinder,

    Is there any article explaining Cost of Quality in your blog?

    Regards
    Manisha

    ReplyDelete
    Replies
    1. Hi Manisha,

      I don't think so. Usually I write on topics that are somewhat obscure and not well explained in books.

      If you mention your queries on COQ, I can try to clarify them.

      You can also post them on PM Hangout if you want more space and convenience.

      Thanks for bringing this up.

      Best regards,
      Harwinder

      Delete

Please do not include URLs (links) in your comments as any comment with links would be deleted automatically.

Other interesting posts