· Harwinder Singh · PMP · 6 min read
Planned Value (PV) vs Earned Value (EV) in Earned Value Management (EVM)
Difference between Planned Value, Earned Value, and Actual Cost in Earned Value Management under Project Cost Management.

What’s the difference between Planned Value (PV), Earned Value (EV), and Actual Cost (AC) in Earned Value Management (EVM)? This is one of the most frequently asked question by people when they first come across the EVM concepts. I got this question in the email (not for the first time though), and my first instinct was to direct the sender to one of my blog posts. When I tried to look for the post, I was really surprised to know that though I have several posts on advanced EVM concepts such as ETC, EAC, TCPI etc., I don’t have any post on the most important EVM topic - Planned Value vs Earned Value. Better late than never, this is my attempt to cover this topic. We’ll also add Actual Cost (AC) to the mix, though most people don’t have problem understanding AC. As usual, we’ll learn by examples and exercises.
PMBOK® Guide, 5th Edition Definitions
Let’s look at the PMBOK® Guide definitions of these terms first.
Definition of Planned Value (PV)
The authorized budget assigned to scheduled work.
Definition of Earned Value (EV)
The measure of work performed expressed in terms of the budget authorized for that work.
Definition of Actual Cost (AC)
The realized cost incurred for the work performed on an activity during a specific time period.
The above definitions are pretty straight-forward and self-explanatory, right? Well, not for most beginners. Here are the simplified definitions sourced from BrainBOK PMP Flashcards. The keywords are underlined.
Simplified Explanation
What’s the difference between Planned Value (PV) and Earned Value (EV)?
Planned Value is the estimated (monetary) value of the work planned to be done, whereas Earned Value is the estimated (monetary) value of the work actually done.
What’s the difference between Earned Value (EV) and Actual Cost (AC)?
Earned Value is the estimated (monetary) value of the work actually done, whereas Actual Cost is the amount actually incurred for the work done.
Trick to remember PV, EV and AC
PV => Estimated value / work planned to be done
EV => Estimated value / work actually done
AC => Actual cost incurred
5 Practice Questions on Earned Value Management
As such, the concepts are pretty straight forward but when applied to exam questions, things get tricky. Most people don’t have a problem in understanding Actual Cost (AC). Let’s apply the above trick to sample questions.
Question 1
A project team had planned to accomplish $25,000 worth of work to date. It has spent $23,000 to date, and accomplished $20,000 worth of work. What is PV, EV and AC of the project as of today?
Based on this information, what is the estimated value of the work planned to be accomplished till date? It is $25,000. This is the PV.
What is the estimated value of the work actually accomplished? $20,000. This is the EV.
What is the amount actually spent? $23,000. This is the AC.
Easy, isn’t it? Not so fast. Let’s consider a slightly more challenging problem.
Question 2
A project has 10 work packages, each estimated to cost $100,000. The project team had estimated to complete 3 work packages at the end of three months. However, they managed to complete only 2 work packages in 3 months and spent $300,000. What is the PV, EV and AC of the project at the end of three months?
PV is the estimated value of the work packages planned to be completed in 3 month. 3 work packages were planned to be completed in 3 months. The estimated value of each work package is $100,000. Therefore, PV = 3 x $100,000 = $300,000.
EV is the estimated value of work packages actually completed. 2 work packages were actually completed and their value is 2 x $100,000 = $200,000
AC is the actual cost incurred in 3 month i.e. $300,000.
Feeling better now? Let’s see how well you fare on the next one.
Question 3
A project has a total budget of $100,000. Two months into the project, it has used $30,000 of its total budget to accomplish work that was estimated to cost $25,000. What is the PV, EV and AC?
What does $25,000 represent in this question? PV or EV? Apply the knowledge that you’ve acquired so far.
The work that was estimated to cost $25,000 has already been accomplished. So, it is our EV, not PV. Tricky, isn’t it?
What is the PV? We do not have enough information in the question to determine PV for the project.
What is actually spent? $30,000. This is our AC.
Let’s continue.
Question 4
A project has a total budget of $100,000 and is estimated to take 10 months to complete. After 5 months, it is estimated to complete 50% of its work at the cost of 60% of its budget, but it actually accomplished only $40,000 worth of the work, and spent 50% of its budget. What is the PV, EV and AC of the project after 5 months?
What is the estimated value of work planned to be completed in 5 months? It is 60% of the budget, which is $60,000. This is the PV.
What is the estimated value of work actually completed in 5 months? It is $40,000. This is the EV.
What is actually spent? 50% of the budget i.e. 50% of $100,000, which is $50,000. This is the AC.
Getting a hang of it now? Get ready for the final showdown.
Question 5
A project has 10 work packages and each work package is estimated to take 1 month to complete. The first 5 work packages are estimated to cost $12,000 each, and the next 5 $8,000 each. At the end of month 5, the first 4 work packages were completed at the cost of $48,000. What is PV, EV and AC of the project at the end of month 5?
The following table lists the PV after each month.
Month | PV ($)
1 | 12,000
2 | 24,000
3 | 36,000
4 | 48,000
5 | 60,000
6 | 68,000
7 | 76,000
8 | 84,000
9 | 92,000
10 | 100,000
The PV after month 5 is $60,000.
4 work packages were actually completed after month 5. Their estimated value is 4 x $12,000 = $48,000. This is the EV.
AC is the cost actually incurred i.e. $48,000.
I hope you found this post useful. If you have other EVM sample questions on PV, EV or AC that you have trouble with, post them in the comments below. I’ll try to address them. I also intend to cover all the topics listed on 80+ Commonly Confused Concepts for the PMP Exam in future.
Image credit: Flickr / carbonnyc
- Sample Questions
- Earned Value Management (EVM)
- PMP Formulas
- Monitoring and Controlling
- Commonly Confused Concepts
- Study Notes
15 Comments
Moderated — submissions appear after approval.
- VS Venkatraman imported
Mr. Harwinder, I find your explanations clear and precise. In fact, your explanation of PTA & Configuration helped me to understand the concepts better. I have a doubt, regarding EV and PV. I read in one of the internet resources that EV can not exceed PV and they gave reference to PMBOK, Fig 7-12. While I understand that at the end of the project, this statement is true as EV will approach BAC; this statement need not be true in the middle of the Project. If there is a question in the PMP exam on this without explaining what stage the project is in; how to answer? best regards Venkat
- Harwinder Singh imported
Hello Venkat, Thanks for your encouragement. I've not gone into the formulae for SV and SPI in this post and was planning to cover them in a subsequent post. But SV = EV - PV. If EV cannot exceed PV during the course of the project, then that implies that the project can never be ahead of schedule (SV > 0). That's obviously not the case. EV can be less than, equal to, or more than PV during the course of the project. At the end of the project, EVM doesn't have a meaning. So for the exam questions, if you are asked to calculate EV or any of the EVM indices or indicators, you can assume that the project is in progress. Does that answer your question?
- Anwer imported
Planned Value is the approved value of the work to be completed in a given time. It is the value that you should have been earned as per the schedule. Earned Value is the value of the work actually completed to date. If the project is terminated today, Earned Value will show you the value that the project has produced.
- Yousif Terrfi imported
many thanks very useful
- Harwinder Singh imported
You are welcome. Glad you found it useful.
- scott
In Question 4 above, the EV and AC are both below the PV, which means you've spent less than planned, but also got less work done than planned. Logic would say "spend more to get caught up, otherwise you'll miss the schedule with money in the bank." Is there an equation, using PV, EV and AC that will tell you if the money you have NOT spent is enough to get back on plan? To me that's the ultimate question that is begging to be answered and in my research I cannot find anybody that talks about it. For my project, all of the spending is on resources. No hardware, materials, etc. So we basically have a linear plan for estimated work to complete (assuming my resources stays the same). I am currently in the situation above, mainly because I have one resource that's been moved to another project. How do I know if the money I'm banking monthly is the equivalent to the work that hasn't been completed?
- Harwinder Singh
Hi Scott, We cannot draw any conclusions from the values of PV, EV and AC. You have to calculate SPI, CPI, SV, CV, EAC, ETC, and TCPI to answer the questions that you asked. If your CPI is below 1, then you are behind on cost. In other words, the money that you have in the bank is not sufficient to complete the remaining work if the work continues at the same rate. Hope that helps.
- Muhammad Ayaz
Nice article I have a question and need your help, please. I had a project for which i carried out Earned Value Analysis using Microsoft Project. At the end of the project, when the project was physically 100 percent complete, my SPI turns out less than 1, which according to literature, must be equal to 1. In other words, MS Project displays that at the end, my EV is less than PV. Is such sort of scenario is possible for a completed proejct?
- Harwinder Singh
Thanks, Ayaz. Are you using % Complete instead of Physical % Complete? Here's a note about MS Project: "You can calculate earned value by manually recording the Physical % Complete instead of letting Project calculate % Complete, which is actual duration divided by total duration." See if that applies to your case. Hope it helps.
- Muhammad Ayaz
Thanks for your response. As far as the % complete is concerned, both the relevant columns of %complete and Physical % complete are showing 100%comoplete for all tasks, but still, the Earned Values is not equal to PV at the end/completion of the project. I don't know what has happened
- Harwinder Singh
There's a manual and an automatic calculation option. Which option are you using?
- luis bernal
Could you please help me with this question? I solved an exercise and I got PV=12, AC=12, and EV=10. I must apply 20/80 rule. I do not how Thanks Luis
- Harwinder Singh
Hi Luis, I'm not clear on your question. What is the exercise that you solved? There's no 20/80 rule to be applied in this context. If you post the question clearly, I may be able to help.
- Olufemi
Good day Mr Harwinder, I really find your explanation clear and helpful, wish I found this earlier. However, I have two questions bothering me. 1) are EV, PV, AC only useful while the project is ongoing? Or can they still be used to analyse a project at final completion. 2) at the end, will overall PV always equal to the total budget?
- Harwinder Singh
Hello Olufemi, Thanks for your feedback. Glad to know that you found the explanation useful. Those are great questions especially the first one. 1) Earned value calculations are useful only while the project is in progress. These calculations are used to take corrective and/or preventive actions to keep the project performance in line with the baselines. 2) Yes, the total PV is equal to the BAC. Hope that helps.








